The short answer
A kitchen remodel runs in this order: design and ordering, demolition, rough plumbing and wiring, inspection, drywall, paint, cabinets, countertop template, countertops, backsplash, then appliances and fixtures.
Cabinets and countertops have the longest waits. Cabinets are ordered before demolition starts, and countertops can only be measured after the cabinets are installed.
The steps, one by one
- Design and selections. Layout, cabinet order, appliance models, sink, faucet, lighting plan.
- Permits. Needed when plumbing, wiring, gas or walls change.
- Demolition. Cabinets, counters, flooring and any walls that are leaving.
- Framing changes. New openings, moved walls, floor repairs.
- Rough plumbing, electrical and venting. New lines to the sink, dishwasher, refrigerator and range, circuits for the appliances, and the hood duct.
- Rough inspection. Before any wall is closed.
- Insulation and drywall. Then primer and the first coat of paint.
- Flooring. Before or after the cabinets, depending on the material.
- Cabinets. Set level and fastened.
- Countertop template. The fabricator measures the installed cabinets.
- Countertops. Installed once fabricated, with the sink.
- Backsplash. Tiled after the countertop is in.
- Finish plumbing, electrical and appliances. Faucet, disposal, lights, outlets, range, dishwasher.
- Final paint, punch list and final inspection.
What has to be decided before demolition
The rough work is built to fit specific products. Change the product later and the wall has to be opened again. Have these chosen, with model numbers, before anyone swings a hammer:
- every appliance, because each has its own size, clearances and electrical or gas requirement;
- the sink and faucet, which set the drain height and the holes in the countertop;
- the range hood, which sets the duct size and route;
- the lighting plan, including under-cabinet lights and their switches;
- the position of each outlet along the counter and in the island.
Does the floor go in before the cabinets?
| Flooring | Usual order | Why |
|---|---|---|
| Tile | Before cabinets | The floor runs wall to wall, so a future cabinet change does not expose bare subfloor |
| Nail-down or glue-down hardwood | Before cabinets | Same reason, and the appliances sit at floor height |
| Floating vinyl plank or laminate | After cabinets | A floating floor has to move with the seasons and should not be pinned under cabinets |
Either way, the finished floor height has to be known before the cabinets are set. A dishwasher that fits today can be trapped by a thicker floor added later.
The countertop gap
Stone and quartz countertops are cut to the installed cabinets, to a fraction of an inch. So there is always a wait between the day the cabinets go in and the day the countertops arrive. During that time the kitchen has cabinets and no sink.
Plan for it. A temporary plywood top with a utility sink keeps the room usable, and the fabricator's schedule should be on the calendar before demolition.
Living without a kitchen
- Set up a temporary kitchen in another room: the old refrigerator, a microwave, a toaster oven and a table.
- Decide where dishes get washed. A laundry sink or a bathroom vanity will do.
- Pack the kitchen in labeled boxes and keep out one box of daily items.
- Expect dust. Doorways are sealed with plastic, and some still gets through.
Why one company for the whole kitchen
One company running the plumbing, wiring, drywall, cabinets and tile keeps the steps in order. See kitchen remodeling. If you are still on the layout, read how much space you need around an island, and for permits, kitchen and bathroom permits in Pennsylvania.
About this guide
General guidance from Pro Elite Builders, last reviewed on November 19, 2026. Every house is different, and product instructions and local codes take priority over anything written here.