Stud partitions framed on a new concrete floor, before any wiring or drywall

What Order Should You Renovate a House In?

Remodeling and additionsBy Pro Elite Builders, PA HIC #PA215210Checked 3 min read

The short answer

Work from the structure outward and from the top down. Fix what holds the house up, make the shell weathertight, run the pipes, wires and ducts while the walls are open, then insulate, close the walls and finish. Floors and final paint come last.

Nearly every expensive do-over comes from breaking that order: new floors laid before the plumbing moved, or a kitchen installed under a roof that still leaks.

The sequence, in ten steps

  1. Plan and permits. Layout, drawings, selections with long lead times, and the permits your municipality requires.
  2. Demolition. Everything that is leaving comes out, so the real condition of the framing, wiring and plumbing is in view.
  3. Structural work. Beams, posts, floor framing, subfloor repairs and any walls that move.
  4. Roof, windows and exterior doors. The shell is made dry before anything that water can ruin goes inside.
  5. Rough plumbing, electrical and heating. Pipes, wires and ducts run through the open walls and floors.
  6. Rough inspections. The inspector sees the framing and the rough work before it is covered.
  7. Insulation. Exterior walls and ceilings, with air sealing done first.
  8. Drywall. Hung, taped, finished and primed.
  9. Finishes. Cabinets, countertops, tile, flooring, trim, doors and paint, then fixtures and appliances.
  10. Final inspection and punch list. The last corrections, then the walkthrough.

Why structure and the shell come first

Structural work shakes a house. It cracks plaster, opens floors and makes dust. Do it after the kitchen is in and you pay to repair the kitchen.

Water is the other reason. Drywall, insulation, hardwood and cabinets are all ruined by it. A roof that leaks or a window opening that is not flashed has to be fixed before those materials arrive.

Stud partitions framed on a new concrete floorNear Boyertown · May 2026
The framing stage on our bank barn job near Boyertown. Walls are up and nothing is covered yet. This is when pipes and wires go in.

The walls are open once

The rough-in stage is the cheapest moment in the whole job to add things. An extra outlet costs little now and a lot after paint. Decide these before the walls close:

  • where every switch, outlet and light fixture goes;
  • where the sink, toilet, tub and shower sit;
  • blocking in the walls for grab bars, a wall-hung television, heavy mirrors and shelves;
  • cable and network runs;
  • any future work you can prepare for, such as a capped line for a bathroom you plan to add later.

Where the order bends

SituationWhat changes
You are living in the houseThe work is phased by floor or by room, and one bathroom stays working at all times
Something is leaking nowThat repair jumps the line, ahead of plans and permits for the rest
Site-finished hardwood floorsSanding and finishing happen after drywall and before the final coat of paint
Winter startInterior work goes first where the shell is already sound, and exterior work waits for weather

If you renovate in phases over several years

Keep the same priorities. Spend first on what keeps water out, then on structure, then on wiring, plumbing and heating. Kitchens, baths and floors come after that. The finishes you can see are the last place to put money, because everything under them can damage them.

Plan the whole house once, even if you build it in three stages. A plan shows which walls will be opened later, so nobody tiles a wall this year that has to come down next year.

How Pro Elite Builders runs it

The sequence only works when one party controls it. On a whole-home remodel Pro Elite Builders handles the framing, the roof, the drywall, the floors, the kitchen and the baths under one contract, in this order. For what your municipality will want to inspect along the way, see kitchen and bathroom permits in Pennsylvania.

About this guide

General guidance from Pro Elite Builders, last reviewed on November 19, 2026. Every house is different, and product instructions and local codes take priority over anything written here.

    Questions

    Quick answers

    Should floors or paint come first?

    Prime and paint ceilings and walls before the finished floor goes in, then do the final coat and touch-ups after the floor and trim are installed. Site-finished hardwood is sanded and finished before that final coat.

    Should I replace windows before siding?

    Yes, or do both together. The window flashing has to tie into the layer behind the siding, and that is easy only when the siding is off.

    Should I remodel the kitchen or the bathroom first?

    Start with the one that has a plumbing or water problem. If they share a wall or a drain stack, do them together so that wall is opened once.

    Does the roof come before interior work?

    Yes. A new interior under a failing roof is at risk from the first heavy rain.

    Keep reading

    • Front of a two-story rowhouse with new windows set into reframed openingsLebanon · November 2025

      Remodeling and additions

      Renovating a row home in Lancaster, PA

      Shared brick walls, a flat rear roof, plaster on lath and wiring older than your grandparents. What a Lancaster row home hides, and what to check before you buy materials.

      4 min read

    • Contractor's truck, trailer and materials arriving at a job site in Lancaster CountyWest Earl Township · May 2026

      Hiring a contractor

      What is a PA HIC number, and how do you verify it?

      Pennsylvania registers home improvement contractors. It does not license them. How to look a number up, and what the result tells you.

      4 min read

    Free estimate

    Have a project in mind? We'll come out and look at it.

    Tell Pro Elite Builders what you need done. We'll call you and come out to look at the job the same day or within 3 days, then send a written proposal with the scope, the price and the schedule.

    • On site the same day or within 3 days
    • Written proposals
    • PA HIC #PA215210

    Request a free estimate

    1. 1What do you need?
    2. 2Show us the job
    3. 3How do we reach you?

    What do you need?

    What do you need? Choose all that apply.

    or call us at (610) 858-5650

    CallFree estimate